The Visayas Grid is expected to experience tighter power reserves on Monday, November 23, with the National Grid Corporation of the Philippines (NGCP) declaring red and yellow alerts due to reduced generation capacity.
In its advisory, NGCP said a red alert would be in effect from 5 p.m. to 6 p.m., while yellow alerts would cover 3 p.m. to 5 p.m. and 6 p.m. to 8 p.m. A red alert means available supply is insufficient to meet consumer demand and the grid’s regulating requirements, while a yellow alert indicates that reserves are inadequate to meet contingency requirements.
The alert declarations were attributed to several power plant outages and reduced generating capacities. These include an unplanned outage involving Therma Visayas Inc. (TVI) Unit 2, as well as planned maintenance outages at units operated by Palm Concepcion Power Corporation and KEPCO SPC Power Corporation. NGCP also reported limited power imports from Mindanao due to outages affecting GNPower Kauswagan Unit 3, STEAG Unit 2, and FDC Unit 3.
As of the advisory, 21 power plants were operating at reduced capacities, accounting for 612.5 megawatts of unavailable capacity. Several other facilities were also on forced or planned outages, with some having been offline since previous years.